About company News Production Equipment Certificates Prices Publications

Plant of Production sewed-in mats

 

main ->  equipment -> plant of production sewed-in mats

 

Equipment description

The line is meant for the production of the sewed-in mats.

Technological scheme of the production.

The equipment infrastucture

The Plant consists of:

  • Supplying conveyer
  • Fiber distributor
  • Fiber carpet supply conveyer
  • Cutting unit
  • Sewing machine
  • Electric equipment, including control panel
  • Reception conveyor with the pressing shaft
  • Packing Table
  • Driving gear
  • Conveyor plate with the barrier
  • Service platform
  • Spooler
  • Binding elements, that provide non-stop production process
  • Length setting unit
  • Pressing drum
  • Transversal distributor production line
  • Supply conveyor
  • Conveyor driving gear (chain transmission)
  • Distributor driving gear
  • Separation driving gear
  • Drawing out unit

The Line WPM is supplied by an electric equipment, including KIP and A, and its purpose is to ensure control and to support the set parameters of the line.

Technical-economic indicates

#

Name of Indices

Quntity of Indices

1

Productivity, m3/hour

8

2

Stitch step, mm

20:100

3

Distance between needles, mm

100

4

Product width, mm

100:900

5

Product thickness, mm

10:120

6

Overall dimensions of the line, mm not more
length
width
height


20 000
5 000
1 500

The personal qauntity

Sewing machine is operated by 2 operators and one adjuster, The latter can operate several technology lines.

Equipment service life

Service life of the equipment is not standardized.

Outline of the operation process

Basalt canvas (linen) from the line of the basalt super fine (thin) fiber through the conveyor is fed to the distributor, from the transversal production line to the supplying conveyor and cutting unit, then to the sewing machine where the canvas (linen) is stitched and fed to the packing table.

The terms of the equipment production

The production term of the line WPM is 1 month.

Assembling, installation and set-up works take up 1 week.